RFQ for the civil works package is likely to be floated in Q2 2023. – Software update: Power projects, 2 Mar 2023
Mar 02, 2023
Rs. 4446 crore greenfield pumped storage project: RFQ coming up
Detailed design and drawings of the project have been completed
PMC has been selected.
RFQ for the civil works package is likely to be floated in Q2 2023.
Rs. 550 crore greenfield hydroelectric power project: PMC package
Drilling and drifting works at the site are in progress.
Hydrology report is in progress.
RFQ for the PMC package is likely to be floated in April 2023