Bulletin Updates

LOA for HM package in Q2 2023 – Software update: Power projects, 28 Feb 2023

Feb 28, 2023

Rs. 5000 crore greenfield hydroelectric project: LOA soon

Civil work contractor has completed the mobilization of equipment.

LOA for HM package in Q2 2023

Bid evaluation is in progress for the EM works.

RFQ for the C&I system package is likely to be floated by April 2023.

Rs. 9470 crore greenfield pumped storage project: RFQ ahead

The TEC of the DPR has been granted

Forest clearance stage 1 has been approved but forest clearance stage 2 is pending.

RFQ for the civil works package is likely to be floated in May 2023