RFQ for the civil works package is likely to be floated in Q2 2023. – Software update: Power projects, 16 Feb 2023

Feb 16, 2023

Rs. 2020 crore greenfield hydroelectric power project : RFQ ahead

The hydrology report of the project has been approved by the CWC.

PMC has been selected for the project.

RFQ for the civil works package is likely to be floated in Q2 2023.

Rs. 2000 crore greenfield hydroelectric power project : Civil works package coming up

Forest clearance stage 2 is pending at DFO.

Bid evaluation is in progress for the civil works package (lot-1).

RFQ for the civil works package (lot-2) is likely to be floated in April 2023

Rs 750 crore 400 kV D/C Koppal-Narendra Transmission Line project : RFQ ahead

Forest clearance stage 1 and stage 2 have been approved by DFO

Fabrication work for the lattice tower is yet to be started.

RFQ for the P/S package is likely to be floated in March 2023.