Total route length of this transmission line is approximately 150 km. – Software update: Power projects, 3 Feb 2023

Feb 03, 2023

Rs 490 crore 765 kV D/C transmission line from Ahmedabad to Banaskantha: S/S works ahead

Detailed survey and investigation have been completed for the transmission line.

Total route length of this transmission line is approximately 150 km.

RFQ for the GIS S/S works package is likely to be floated in April 2023.

Rs 12700 crore greenfield pumped storage project: RFQ ahead

Geotechnical investigation and topographical survey have been completed

Forest clearance stage 1 is pending at the regional office.

RFQ for the PMC package is likely to be floated in March 2023.

Rs 4172 crore greenfield pumped storage project stage-I: Civil works coming up

TEC of the DPR has been approved

Forest clearance stage 2 is pending at DFO.

RFQ for the civil works package is likely to be floated in April 2023

Rs 900 crore greenfield combined cycle gas-based thermal power project: EPC package

Modification of the EIA / EMP report has been completed

Forest clearance is not required for the project.

Tender has been floated for the EPC package for main plant work and a pre-bid meeting held soon.

Rs 820 crore 765 kV D/C transmission line from Navsari to Padghe: Land acquisition completed

The forest clearance stage -2 has been granted by the DFO.

Approval from PTCC, civil aviation, and defense have been granted.

RFQ for the ACSR moose conductor package is likely to be floated in March 2023.

Rs 2700 crore greenfield hydroelectric project: RFQ ahead

Forest clearance stage 1 and wildlife clearance is yet to be granted.

Geological investigation and topographical survey have been completed.

RFQ for the PMC package is likely to be floated in April 2023.

Get in touch with us for more on these project