Total route length of this transmission line is approximately 150 km. – Software update: Power projects, 3 Feb 2023
Feb 03, 2023
Rs 490 crore 765 kV D/C transmission line from Ahmedabad to Banaskantha: S/S works ahead
Detailed survey and investigation have been completed for the transmission line.
Total route length of this transmission line is approximately 150 km.
RFQ for the GIS S/S works package is likely to be floated in April 2023.
Rs 12700 crore greenfield pumped storage project: RFQ ahead
Geotechnical investigation and topographical survey have been completed
Forest clearance stage 1 is pending at the regional office.
RFQ for the PMC package is likely to be floated in March 2023.
Rs 4172 crore greenfield pumped storage project stage-I: Civil works coming up
TEC of the DPR has been approved
Forest clearance stage 2 is pending at DFO.
RFQ for the civil works package is likely to be floated in April 2023
Rs 900 crore greenfield combined cycle gas-based thermal power project: EPC package
Modification of the EIA / EMP report has been completed
Forest clearance is not required for the project.
Tender has been floated for the EPC package for main plant work and a pre-bid meeting held soon.
Rs 820 crore 765 kV D/C transmission line from Navsari to Padghe: Land acquisition completed
The forest clearance stage -2 has been granted by the DFO.
Approval from PTCC, civil aviation, and defense have been granted.
RFQ for the ACSR moose conductor package is likely to be floated in March 2023.
Rs 2700 crore greenfield hydroelectric project: RFQ ahead
Forest clearance stage 1 and wildlife clearance is yet to be granted.
Geological investigation and topographical survey have been completed.
RFQ for the PMC package is likely to be floated in April 2023.