Forest clearance stage 1 is pending at the nodal office. – Software update: Power projects, 25 Jan 2023
Jan 25, 2023
Rs 7484 crore greenfield standalone pumped storage project: PMC package
Drilling work has been completed.
Forest clearance stage 1 is pending at the nodal office.
RFQ for the PMC package is likely to be floated in March 2023.
Rs 7484 crore greenfield standalone pumped storage project: PMC package
Drilling work has been completed.
Forest clearance stage 1 is pending at the nodal office.
RFQ for the PMC package is likely to be floated in March 2023.
Rs 30000 crore greenfield super thermal power project: RFQ ahead
Erection and installation of ESP is an advanced stage of completion.
The tender has been floated for the railway siding works.
RFQ for the ball mill package is likely to be floated in April 2023