Forest clearance for stage 1 and stage 2 has been granted by the DFO. – Software update: Power projects, 11 Jan 2023
Jan 11, 2023
Rs 11030 crore greenfield pump storage project: HM works coming up
Forest clearance for stage 1 and stage 2 has been granted by the DFO.
Bid evaluation is in progress for the EM package.
RFQ for the civil and HM works package is likely to be floated in Q2 2023
Rs 442 crore greenfield hydroelectric project: RFQ ahead
Forest clearance stage 1 is under process at the nodal office
Private land acquisitions are in progress and it is in an advanced stage for completion.
RFQ for the civil work package is likely to be floated by March 2023.