Forest clearance stage 2 is pending at DFO. – Software update: Power projects, 6 Jan 2023
Jan 06, 2023
Rs 1194 crore greenfield hydroelectric project: Civil work package (lot 2) in April 2023
Forest clearance stage 2 is pending at DFO.
Bid evaluation is in progress for the civil work package (lot 1)
RFQ for the civil works package ( lot-2) is likely to be floated in April 2023.
Rs 8374 crore greenfield pumped storage project: Drilling works coming up
Forest clearance stage 1 is pending at the nodal office.
RFQ for the drilling and drifting work is likely to be floated in February 2023
Rs 550 crore greenfield hydroelectric project: RFQ ahead for HM works
Forest clearance stage 2 has been approved by the DFO.
Bid evaluation is in progress for the civil works package.
RFQ for the HM works package is likely to be floated in Q2 2023.
Rs 18668 crore greenfield thermal power project phase-1: BOP works coming up
Bid evaluation is in progress for the CW system package.
Package contractor has been selected for unit transformer work.
RFQ for the ash dyke package is likely to be floated in February 2023.
Get in touch with us for more on these project