Project Event: The bid due for the Feasibility study by conducting Impact Assessment and Soil… – Software update: Fertilizer projects, 16 Dec 2022
Dec 16, 2022
Ammonia Storage Tank Greenfield Project
Cost: Rs 100 Cr.
Project Event: The bid due for the Feasibility study by conducting Impact Assessment and Soil Investigation has been extended from 12 to 19 Dec 2022, Toyo engineering is the single bidder for the 10000 MT double-wall supply with associated facilities on an EPCC- LSTK basis. The project is likely to be commissioned in Q2 FY 2023-2024.
Ammonia-Urea Brownfield Project
Cost: Rs 6000 Cr.
Project Event: RFQ for the HURL township has been extended from 15 Dec 2022 to 3 Jan 2023. RFQ for the additional Dryer unit has been cancelled. The production at the complex has been started in Feb 2022 with 60 % of the production capacity is now on. The construction of the railway line is not completed yet. the complex will transport the urea through the Truck