Ammonia-V Revamp Project
Cost: 102 Cr.
Project Event: Construction as well as procurement is ongoing. The project is likely to be completed in October 2023.
Ammonium Nitrate Melt Greenfield Project
Cost: 188 Cr.
Project Event: Tender for Civil work contractor is likely to be released in January 2023. L&T Hydrocarbon is the LSTK contractor who does the Process license, Supply of Basic Design., Detailed Engineering, HAZOP Studies, and implementation of its recommendation., Procurement, and Supply of all equipment.