Bid evaluation is in progress for the civil works package (lot-1&2) – Software update: Power projects, 13 Dec 2022
Dec 13, 2022
Rs 2223 crore greenfield hydroelectric project: RFQ for the electro-mechanical work ahead
Tender has been floated for hydro-mechanical work but the pre-bid meeting is yet to be conducted
Bid evaluation is in progress for the civil works package (lot-1&2)
RFQ for the EM works is likely to be floated in Q1 2023
Rs 5147 crore greenfield pumped storage project: Hydro-mechanical works in Q1 2023
PMC of the project has been selected
Bid evaluation is in progress for the civil works package (lot- 1&2)
RFQ for the HM works is likely to be floated in Q1 2023
Rs 11351 crore brownfield super-critical thermal power project (stage-V): RFQ for FGD ahead
Erection and installation of the De-NOx system have been completed.
Bid evaluation is in progress for the ball mill system
RFQ for the limestone and gypsum handling plant system package is likely to be floated in January 2023.