Bulletin Updates
Project Event: The bid due date for the replacement of the Urea reactor and Carbamate… – Software update: Fertilizer projects, 12 Dec 2022
Dec 12, 2022
Urea Reactor (R1) and Carbamate Condenser Unit Revamp Project
Cost: 200Cr.
Project Event: The bid due date for the replacement of the Urea reactor and Carbamate Condenser has been extended from 12 Dec to 19 Dec 2022.
Concentrated Nitric Acid Greenfield Project
Cost: 50 Cr.
Project Event: RFQ for the LSTK contractor is likely to be released at the end of January 2023. This is due to a delay in the DFR preparation. A consultant is appointed for the preparation of a Detailed Feasibility Report (DFR). The report preparation is still ongoing.