Bulletin Updates
Forest clearance stage 2 is under process at the regional office. – Software update: Power projects, 7 Dec 2022
Dec 07, 2022
Rs 3909 crore standalone pumped storage project: EPC package in Q1 2023
Forest clearance stage 2 is under process at the regional office.
PPA has already been signed.
Earlier tender for civil and HM packages was canceled.
RFQ for the EPC package for civil and HM package is likely to be floated in Q1 2023.
Rs 4567 crore Supercritical Thermal Power Brownfield Project: Limestone and gypsum handling plant RFQ ahead
Civil works have been completed for BTG and ESP
Sub- the contractor has been selected for the switchyard package.
Bid evaluation is in progress for the absorber system.
RFQ for the limestone and gypsum handling plant will likely be floated in January 2023.
Rs 5000 crore Pumped Storage Project: Civil works (lot-2) RFQ in Q1 2023
The approach road construction has been completed by the state PWD department.
Mobilization works are in progress by the civil works (lot-1) contractor
RFQ for the Civil works package(lot-2) is likely to be floated in Q1 2023
Rs 2321.05 crore greenfield hydroelectric project stage: RFQ for the EPC package in March 2023
EC is under approval.
PMC has been selected for the project.
RFQ for the EPC package for civil and HM work is likely to be floated in March 2023.
Rs 1601 crore greenfield pumped storage hydroelectric project: HM works package RFQ ahead
Forest clearance stage -1 has been obtained and stage 2 is pending at the nodal office.
Pre-bid meetings are yet to be conducted for the civil works package (Lot-2)
RFQ for the HM works package is likely to be floated in Q1 2023
Get in touch with us for more on these project
Log in Start a free trial »

