Bulletin Updates

Forest clearance stage 2 is pending at the DFO – Software update: Power projects, 5 Dec 2022

Dec 05, 2022

Rs 5404 crore greenfield pumped storage project: Locals have started protests against the project

Techno Economic Clearance (TEC) of the project has been granted

Forest clearance stage 2 is pending at the DFO

Villagers and tribal people have started protests against the development of this project and 800 acres of land for R&R activity

PMC has been selected for the project.

RFQ for EPC package for civil and HM work is likely to be floated in Q1 2023

Rs 4766 crore greenfield pumped storage project: PMC package in January 2023

Geotechnical investigation and topographical survey have been completed.

Approval from CWC has been obtained for the hydrology report.

Forest clearance stage 1 is pending at the DFO

RFQ for the PMC package is likely to be floated in January 2023

Rs 11800 crore greenfield pumped storage project: Civil works in the second half of Q1 2023

TEC of the project has been approved by the CEA

CWC has approved the hydrology report of this project.

RFQ Civil works package is likely to be floated in the second half of Q1 2023

Rs 653 crore greenfield hydroelectric project: EPC package in Q1 2023

EC has been granted for the project.

Private land acquisition has been completed.

Forest clearance stage 2 has been approved by the DFO

RFQ for the EPC package for civil and HM works is likely to be floated in Q1 2023

Rs 1800 crore greenfield pumped storage project: PMC package in January 2023

EC of the project is yet to be approved by MoEF.

Forest clearance stage 2 and wildlife clearance are yet to be approved by the MoEF.

RFQ for the PMC package is likely to be floated in January 2023