RFQ for the SIA consultant is likely to be floated in Q1 2023 – Software update: Power projects, 22 Nov 2022
Nov 22, 2022
Rs 4446 crore greenfield pump storage project: SIA consultant in Q1 2023
TOR of the project has been granted by the MoEF
The geotechnical investigation and topographical survey report have been approved by GSI
Bid evaluation is in progress for the EIA consultant. Find out who are the major contenders in the race.
RFQ for the SIA consultant is likely to be floated in Q1 2023
Rs 1800 crore greenfield pump storage project: PMC package is expected by January 2023
Preparation of DPR is in progress.
Capital approval of the project has been granted by the State cabinet committee.
Geological investigation and topographical survey at the site have been completed
RFQ for the PMC package is expected by January 2023
Rs 6010 crore greenfield pump storage project: EIA consultant is likely to float in December 2022
The owner has signed an MOU with the State Government for the development of the project.
TOR of the project has been granted by the MoEF
RFQ for the EIA consultant is likely to float in December 2022.