Project Event: 70 % of construction work has been completed, Installation of main units is… – Software update: Fertilizer projects, 7 Nov 2022

Nov 07, 2022

Phosphoric acid Expansion Project

Cost: Rs 130 Cr.

Project Event: 70 % of construction work has been completed, Installation of main units is ongoing, the project is likely to be completed in January 2023 in place of December 2022.

Ammonia/Nitric Acid/SOP Greenfield Project

Cost: Rs 200 Cr.

Project Event: The company is still talking with a local contractor for the hiring of an LSTK contractor, and that is likely to be completed in December 2022. The company has elicited the environmental clearance for the project in April 2022