Bulletin Updates
Software update: Fertilizer projects: Cost: Rs 100 Cr., Cost: Rs 6000 Cr. – 2 Nov 2022
Nov 02, 2022
Ammonia Storage Tank Greenfield Project
Cost: Rs 100 Cr.
Project Event: RFQ for the ammonia storage tank with associated facilities has been re-released, and the bid due date has been extended from 21 October 18 November 2022, due to a lack of bidders. In the previous RFQ, Vijay Tank was in the race
Ammonia-Urea Brownfield Project
Cost: Rs 6000 Cr.
In Barauni, active contracting is still on even as urea production has started.