Bulletin Updates
Project Event: The company is talking with a local contractor, which is likely to be… – Software update: Fertilizer projects, 1 Nov 2022
Nov 01, 2022
GSSP/GBSSP/GZSSP/GPG/BSP/BSG Expansion Project
Cost: Rs 48 Cr.
Project Event: The company is talking with a local contractor, which is likely to be finalized in January 2023, EIA study has been completed, final proposal for the environmental clearance has been submitted in October 2022
DAP Expansion Project
Cost: Rs 20 Cr.
Project Event: The project has elicited capital approval as well as environmental clearance, RFQ for the LSTK contractor is likely to be released in Q4 FY 2022-2023