Forest clearance stage 2 has been accorded by the DFO. – Software update: Power projects, 1 Nov 2022
Nov 01, 2022
Rs 820 crore construction of 400KV Transmission line: P/S work is likely to be floated in December 2022
Forest clearance stage 2 has been accorded by the DFO.
Approval from Railway, Defence, PTCC, and Civil aviation has been granted.
The soil test is completed and pilling and foundation works have been completed for the lattice tower.
Land acquisition works completed for substation works and the contractor has been selected for the S/S works.
RFQ for the P/S works is likely to be floated in December 2022.
Rs 2020 crore greenfield hydroelectric project: PMC package in December 2022
The hydrology report for the same has been approved by the CWC.
Forest clearance for the same is pending at the regional office.
The geotechnical investigation and the topographical survey report have been approved by the GSI.
The approach road construction was getting affected due to unfavorable weather conditions and critical geological terrain.
RFQ for the PMC package is likely to be floated in December 2022.
Rs 1512 crore greenfield multipurpose project: HM works in January 2023
Civil work (lot-1) contractor has completed the mobilization of equipment at the site. Know who the contractor is
Bid evaluations are in progress for the civil works package (lot-2). Get to know who the bidders are
RFQ for the HM work is likely to be floated in January 2023 instead of Q4 2022
Rs 3000 crore greenfield hydroelectric project: Pre-bid meeting for EM work completed
Forest clearance stage 1 and 2 has been granted by MoEF.
The Prime minister has laid the foundation stone for the project.
Boring work for HRT is in the initial phase.
Pre-bid meeting has been completed for the EM work
RFQ for the EOT crane package is likely to be floated in Q1 2023