Rs 5200 crore super-critical brownfield thermal power project: PT plant package is likely to be floated in November 2022
Pilling and foundation work at the BTG area have been completed.
Sub-contractor has been selected for the AHP works.
The coal linkage issue has been resolved by the CIL.
Bid evaluations are in progress for the wagon tippler package
RFQ for the PT plant package is likely to be floated in November 2022.
Rs 850 crore construction of 765KV Transmission line: P/S works in December 2022
Forest clearance stage 2 has been accorded by the DFO.
Approval from PTCC, civil aviation, and defense have been granted.
Private land acquisition is in progress for the T/L works and it is in the advanced stage of completion.
Land acquisition was completed for substation works.
RFQ for the P/S works is likely to be floated in December 2022.
Rs 4200 crore greenfield hydroelectric project: HM works package in January 2023
Forest clearance 2 has been accorded by the DFO.
Civil works contractor has been selected and mobilization of equipment has been completed by the contractor
Boring works are in progress for HRT.
RFQ for the HM works package is likely to be floated in January 2023 instead of Q4 2022.
Rs 5150 crore greenfield pumped storage project: HM works package in December 2022
Construction of the approach land to the dam site has been completed.
PMC has been selected.
Pre-bid meetings have been completed for the civil works package
RFQ for the HM works package is likely to be floated in December 2022.