RFQ for the 400KV GIS s/s works package will likely be floated in December 2022 – Software update: Power projects, 20 Oct 2022

Oct 20, 2022

Rs 227 crore construction of 400KV Transmission line: S/S works package in December 2022

S/S site has been changed as suggested by the MOP and CEA

Approval from PTCC, railway, civil aviation, and defense is yet to be granted

Rerouting of the transmission line to avoid an eco-sensitive zone with minimum use of forest area has been completed

RFQ for the 400KV GIS s/s works package will likely be floated in December 2022

Rs 550 crore greenfield pumped storage project: Civil package(lot-2) in December 2022

Construction of the approach road has been completed

Hydrology report has been approved by the CWC

PMC has been selected for the same project

Pre-bid meeting is yet to be conducted for the civil works package(lot-1)

RFQ for the Civil package(lot-2) is likely to be floated in December 2022

Rs 18200 crore greenfield off-stream closed-loop pumped storage project: EPC package for the main plant works in Q1 2023

Forest clearance stage 1 is pending at the DFO and stage 2 is pending at the nodal office

Drilling and drifting works are in progress at the site

Geological investigation and topographical survey at the site have been completed and it was approved by GSI

PMC has been selected for the project

RFQ for the EPC package for main plant works is likely to be floated in Q1 2023

Rs 7000 crore greenfield multipurpose project: EM works package in January 2023

Land acquisition and resettlement have been completed

Forest clearance stage 1 and stage 2 have been granted by the DFO

Contractor has been selected for the civil works package

Pre-bid meetings have been completed for HM works

RFQ for the EM works packages likely to be floated in January 2023

Rs 8500 crore greenfield standalone pumped storage project: Civil works package (lot-1) in Q1 2023

Forest clearance stage 1 has been approved by DFO but forest clearance stage -2 is pending at the regional office.

Public hearing has been completed

EIA/ EMP study report has been prepared by Vimta Labs and it has been approved by the MoEF

Preparation of DPR has been completed and it was approved by CEA

EPC has been selected for the project

RFQ for the civil works package (lot-1) is likely to be floated in Q1 2023

Rs 3000 crore greenfield hydroelectric project: DPR works tender in November 2022

TOR has been granted by the MoEF

Construction of the approach road is in progress it is in the final stage of completion

FC stage-1 is pending at the nodal office

Hydrology report has been completed and it is yet to be approved by the CEA

RFQ for the drilling and drifting works is likely to be floated in November 2022

Get in touch with us for more on these projects