RFQ for the ball mill system package is likely to be floated in December 2022. – Software update: Power projects, 17 Oct 2022
Oct 17, 2022
Rs 8730 crore greenfield supercritical thermal power expansion project: Ball mill package in December 2022
AHP work has been delayed due to the NGT issue.
Civil and structural works have been completed and the installation of pressure parts is in an advanced stage of completion.
PG test has been completed for ESP.
RFQ for the ball mill system package is likely to be floated in December 2022.
Rs 3200 crore greenfield hydroelectric project: Civil works package (lot-1) in January 2022
CEA recommended modifications of DPR in the e-flows design parameter
Private land acquisition and Public hearings were completed for the same
RFQ for the civil works package (lot-1) is likely to be floated in January 2022.
Rs 7500 crore greenfield standalone pumped storage project: SIA consultant in Q1 2023
Forest clearance stage 1 is pending at the nodal office.
Construction of the approach road is in progress and it is in an advanced stage of completion.
Geotechnical investigation and topographical survey report are yet to be approved by GSI.
Drilling works at the site are in progress and drifting work is yet to be started.
RFQ for the SIA consultant is likely to be floated in Q1 2023.
Rs 305 crore construction of 400KV Transmission line: P/S works in November 2022
Forest clearance stage -1 has been approved by DFO but Stage 2 is pending at the nodal office.
Approval from PTCC, railway, civil aviation, and defense is yet to be granted.
Bid evaluations are in progress for the sub-station works.
RFQ for the 400kv P/S works is likely to float in November 2022.