Bulletin Updates

Forest clearance stage 2 is pending at the DFO. – Software update: Power projects, 14 Oct 2022

Oct 14, 2022

Rs 3402 crore greenfield hydroelectric project: PMC works package is likely to float in January 2023

Forest clearance stage 2 is pending at the DFO.

GSI has approved the geotechnical investigation and topographical survey.

Private land acquisition is in progress and it is in the advanced stage of completion

Drilling and drifting works have been completed at the site.

RFQ for the PMC works package is likely to be floated in January 2023.

Rs 4567 crore greenfield supercritical thermal power brownfield project: Absorber system package in November 2022

Civil works have been completed for BTG and ESP.

Erection of pressure parts has been delayed due to the slow mobilization of equipment at the site.

Sub-contractor has been selected for the switchyard package.

Erection and installation of the DeNox system is in progress

RFQ for the absorber system package is likely to be floated in November 2022.

Rs 320 crore construction of 132KV Transmission line: S/S package in November 2022

Forest clearance stages 1 and 2 have been granted by the DFO.

Erection and fabrication of lattice towers are in progress.

Erection and installation of P/S works are in progress.

RFQ for the 132 kV GIS S/S package is likely to be floated in November 2022.

Rs 4949 crore greenfield hydroelectric project: EPC package for the transmission line works in December 2022

Contractor has completed the mobilization of equipment at the site. Click on Details for more.

Boring works are in progress for the HRT.

LOA for the EM package is expected by November 2022.

Bidding is under progress for the EOT crane package.

RFQ for the EPC package for the transmission line works is likely to be floated in December 2022.