Bulletin Updates
Forest clearance stage -2 is pending at the nodal office. – Software update: Power projects, 12 Oct 2022
Oct 12, 2022
Rs 2553.6.crore greenfield hydroelectric multipurpose project: Civil works package in December 2022
CEA has approved the DPR.
PPA has been signed by State Government.
Forest clearance stage -2 is pending at the nodal office.
EC is yet to be approved by the MoEF
RFQ for the civil works package is likely to be floated in December 2022.
Rs 3500 crore greenfield standalone pumped storage project: SIA consultant in December 2022
TOR has been granted by the MoEF.
State PWD department has completed the construction of the approach road.
Drilling works at the site are in progress and drifting works are yet to start.
RFQ for the SIA consultant is likely to be floated in December 2022.
Rs 9240 crore greenfield thermal power expansion project: CW System package in November 2022
The project has got approval from the state cabinet committee.
The pilling works are in progress at the BTG site.
Sub-contractor has been selected for the Wagon tippler package
Bidding is under progress for the NDCT package.
Pre-bid meetings are yet to start for the coal mine-III.
RFQ for the CW System package is likely to be floated in November 2022.
Rs 350 crore construction of 400 KV Transmission line: P/S works in November 2022
Forest clearance stage -1 has been granted by the DFO and stage -2 is pending at the regional office.
Approval from PTCC, Civil aviation, and defense have been granted.
Land acquisition is in progress for the transmission line
RFQ for the 400 kV P/S works package is likely to be floated in November 2022.