Phosphoric acid Expansion Project
Cost: Rs 500 crore.
Project Event: The technical bid has been opened and evaluation is still ongoing, Two companies are in the race for Pre-qualification of Vendors for end-to-end study (find out who they are), Financial bid is likely to be opened at the end of October 2022 for this. The finalization is likely to be completed at the end of September 2022. RFQ for the LSTK contractor is likely to be released in November 2022.
SSP-GSSP-NPK-Sulphuric acid Green Field Project
Cost: Rs 50 crore
Project Event: The project is under clearance, public hearing is likely to be started in December 2022, RFQ for the local contractor is likely to be released in January 2022