Forest clearance stage 2 is pending at the nodal office. – Software update: Power projects, 11 Oct 2022
Oct 11, 2022
Rs 696 crore greenfield hydroelectric project: Civil works package(lot-2) in January 2023
Forest clearance stage 2 is pending at the nodal office.
CEA has approved the DPR for the project.
Pre-bid meetings have been completed for civil works(Lot-1). Get the details of those who have attended the pre-bid meeting.
RFQ for the civil works package(lot-2) is likely to be floated in January 2023
Rs 857crore greenfield hydroelectric power project: Civil works package(lot-1) in December 2022
Wildlife clearance has been granted by the MoEF.
SIA report is yet to be approved by the MoEF.
Hydrology report has been approved by the CWC.
Package-wise bids instead of EPC format
RFQ for the civil works package (lot-1) is likely to be floated in December 2022.
Rs 6614 crore off-stream closed loop greenfield pumped storage project: DPR consultant in November 2022
TOR granted by the MoEF
The soil test at the site was completed.
EIA/EMP consultant has been selected.
RFQ for DPR consultants is likely to be floated in November 2022
Rs 108 crore construction of 220 KV Transmission line: S/S package in December 2022
Forest clearance and land acquisition are pending due to issues related to an adjoining zoological park.
Several meetings have been conducted with the state government
Pilling works are in progress at the non -the forest area.
RFQ for 220 KV GIS S/S is likely to be floated in December 2022.
Get in touch with us for more on these projects