Bulletin Updates
The forest clearance for stage 2 has now been – Software update: Power projects, 7 Oct 2022
Oct 07, 2022
Rs 5400 crore greenfield hydroelectric project: Civil works contractors selected; preparation on to float EM package
The forest clearance for stage 2 has now been
Contractor has been selected for the civil works package and mobilization of equipment is about to start. (Find out who the contractor is)
Pre-bid meetings are yet to conduct for the hydro-mechanical works.
RFQ for EM works package is likely to be floated in December 2022.
Rs 830 crore greenfield hydroelectric power project: Know who the PMC is
Preparation of DPR is in the advanced stage for completion
PMC has been selected
Frequent landslides and bad weather have delayed the construction of the approach road.
Land acquisitions have been completed and the first phase of the public hearing has been completed.
RFQ for the civil works package is likely to be floated in December 2022.
Rs 4800 crore thermal Power Station Replacement project: EPC awards sub-contracts
Pilling and foundation works have been completed at the BTG site.
Sub-contractors have been selected for the DM and PT plant (For sub-vendors, the names are given here for reference purposes)
Half of the total requirement will be fulfilled from imported coal.
Additional land acquisitions were completed and it was handed over to the contractor.
RFQ for the Wagon Tripler package is likely to be floated in November 2022.
Get in touch with us for more on these project