Bulletin Updates

FC stages 1 and 2 were granted by the DFO – Software update: Power projects, 29 Sep 2022

Sep 29, 2022

Rs 653 crore construction of 400 KV D/C Transmission line: Moose conductor package in October 2022

Private land acquisition was completed for S/S

Lattice tower works have been completed.

FC stages 1 and 2 were granted by the DFO

Detailed design and drawing of pooling station works have been approved.

RFQ for the moose conductor package is likely to be floated in October 2022.

Rs 990 crore greenfield hydroelectric project: HM works package in Q4 2022

Forest clearance stage 2 has been approved by MoEF.

Construction of the approach road has been completed.

Contractor has been selected for the civil works package(Lot-1).

Bidding is in progress for the civil works package(Lot-2).

RFQ for the HM works package will likely be floated in Q4 2022.

Rs 8112 crore greenfield hydroelectric power project: EPC package for power evacuation in December 2022

Construction of the main access tunnel has been completed before the scheduled time.

Erection and installation of turbine works have been completed but switchyard works are in progress.

Land acquisition works have been completed for the transmission line works.

RFQ for the EPC package for the power evacuation system is likely to be floated in December 2022.

Rs 11370 crore greenfield thermal power expansion project: PT pant package in Q4 2022

Civil and architectural work for the BTG is in progress

Sub-contractor has been selected for the civil and infrastructural work.

LOA has been completed for the Stacker Reclaimer package.

Mabilization of equipment is in progress for the CW system package.

RFQ for the CW system package is likely to be floated in Q4 2022.

Get in touch with us for more on these projects

The full story is for subscribers. Log in to read it, or start a free trial.
Log in Start a free trial »