Ammonium Nitrate and Nitric Acid Greenfield Project
Cost: Rs 1375 Cr.
Project Event: The project is still waiting for environmental clearance, It is likely to be elicited at the end of October 2022. RFQ for the LSTK contractor is likely to be released in November 2022, due to delay in internal discussion.
Nano Urea & Phosphate Rich Organic Manure Greenfield Project
Cost: Rs 250 Cr.
Project Event: RFQ for the contractor and other services is likely to be released at the end of November 2022