Project Event: 30% of the construction has been completed. The erection work for long lead… – Software update: Fertilizer projects, 26 Sep 2022
Sep 26, 2022
Nano Urea Green field Project
Cost: 257 Cr.
Project Event: The viability of the project is being assessed by preparing a Techno-economic feasibility report (TEFR) through a consultant. It requires environmental clearance from MoEF & CC and the company is in the process of getting the same. In parallel, project Management Consultant is also being lined up
NP (20:20:0:13) Fertilizer Expansion Project
Cost: 220 Cr.
Project Event: 30% of the construction has been completed. The erection work for long lead item is still ongoing. Installation is likely to be started in November 2022. The project is likely to be commissioned in December 2023. The company has hired Nuberg for the supply of Design Detailed Engg, Procurement, Supply, Erection, and Commissioning