Forest clearance stage -1 and stage 2 have been granted by the DFO. – Software update: Power projects, 22 Sep 2022
Sep 22, 2022
Rs 325 crore Construction of 400 kV DC T/L: ACSR moose conductor works package in October 2022
NOC from the Inland Waterway Authority of India has been granted.
Forest clearance stage -1 and stage 2 have been granted by the DFO.
Engineering works are in progress for the S/S works.
Approval from civil aviation, defense, and PTCC have been granted.
Fabrication, erection and installation works for P/S is yet to be started.
RFQ for the ACSR moose conductor works package is likely to be floated in October 2022.
Rs 2300 crore greenfield hydroelectric power project: HM works package in November 2022
Hydrology report has been approved by CWC.
PPA has been signed with State Government.
Biddings under progress for the Civil works package. Major civil works contractors have qualified for technical bids.
RFQ for the HM works package is likely to be floated in November 2022.
Rs 11000 crore greenfield thermal power project : Limestone and gypsum handling plant package in Q4 2022
Mechanical completion is in progress for BTG.
Erection and installation of ESP have been completed and the PG test is about to conduct.
Sub-contractor has been selected for the chlorine dosing system.
Civil and structural works have been completed for the ball mill and absorber system.
RFQ for the limestone and gypsum handling plant package is likely to be floated in Q4 2022.