Rs 820 crore construction of 765 kV D/C Transmission Line: EPC package for T/L in October 2022
The detailed survey and investigation have been completed for the T/L.
Approval from PTCC, civil aviation, and defense is in the process.
Several meetings have been conducted with the landowner for land acquisitions.
RFQ for the EPC package for transmission line works is likely to be floated in October 2022.
Rs 830 crore greenfield hydroelectric project: PMC works package in November 2022
Hydrology report has been approved by CWC.
Forest clearance stage -1 is pending at the regional office.
Drilling works at the site are in progress and drifting works are yet to be started.
RFQ for the PMC works package is likely to be floated in November 2022.
Rs 550 crore greenfield hydroelectric power project: HM works package in Q4 2022
Forest clearance stage -1 has been accorded by the DFO but stage -2 is pending at the nodal office.
EC for the same has been granted by the MoEF.
Pre-bid meetings for the same are yet to be conducted for the civil works package.
RFQ for the HM works package is likely to be floated in Q4 2022.
Rs 9800 crore super-critical thermal power expansion project : Absorber system package in October 2022
Civil and structural works of SG are in the advanced stage for completion.
Slow progress of civil works by the sub-contractor.
EPC has de-scoped certain works from the sub-contractor.
NDCT contract has been terminated and its work is at a standstill condition.
Detailed design of FGD works has been approved.
RFQ for the Absorber system package is likely to be floated in October 2022.