The forest clearance (FC) stage-1 was accorded but the stage-2 is pending at the DFO – Software update: Power projects, 19 Sep 2022

Sep 19, 2022

Rs 2700 crore greenfield hydroelectric project: EPC package for in December 2022

The forest clearance (FC) stage-1 was accorded but the stage-2 is pending at the DFO

Preparation of DPR has been completed and it is yet to be approved by the CEA.

The public hearing for the project has been completed.

PMC has been selected for the project.

RFQ for the EPC package for the civil and HM works package is likely to be floated in the second half of December 2022.

Rs 9450 crore super-critical expansion thermal power project: PT Plant package in Q4 2022

The EAC has rejected the additional ash dyke for the Stage-II project.

Pilling and foundation work at the BTG sites have been completed.

Civil and structural works at the BOP sites are in progress.

Sub-contractor selected for stacker reclaimer package

RFQ for the PT Plant package is likely to be floated in Q4 2022.

Rs 2900 crore greenfield pumped storage project: S/S works packages in October 2022

The main access tunnel and ventilation tunnel works have been completed.

The project got delayed due to inter-state boundary issues with states.

HM works contractors have started the construction of the surge shaft and erection of penstock.

Boring works for TRT have been completed and civil works are in progress

Land acquisition of transmission line works was completed.

RFQ for the 440 kV GIS S/S works packages is likely to be floated in October 2022.

Get in touch with us for more on these projects