RFQ for the railway siding package-5 is likely to be floated in November 2022. – Software update: Power projects, 15 Sep 2022

Sep 15, 2022

Rs 16000 crore greenfield super thermal power expansion project: Railway siding works in November 2022

Pre-commissioning works have been completed for the first two units.

Land acquisition has been completed for all railway siding works.

Erection and installation of the absorber system have been completed.

RFQ for the railway siding package-5 is likely to be floated in November 2022.

Rs 960 crore greenfield hydroelectric project: EM package in Q4 2022

The wildlife clearance has been accorded by the wildlife warden.

The civil works contractor(lot-2) has completed the mobilization of equipment at the site.

Construction of HRT works is in progress and excavation of TRT is in progress.

RFQ for the EM package is likely to be floated in Q4 2022.

Rs1800 crore greenfield hydroelectric project : HM works package in Q4 2022.

DPR is completed and it has been approved by the CEA.

EC has been granted by the MOEF.

After several meetings with State Government, the interstate boundary issue have been resolved.

The civil works contractors have completed the mobilization of equipment at the site.

Bidding is in progress for the civil works package(lot-2).

RFQ for the HM works package is likely to be floated in Q4 2022.

Rs 416 crore Construction of 765 kV S/C on D/CTransmission Line: P/S works in October 2022

Wildlife clearence has been granted.

Fabrication of lattice tower is in progress

Bids evaluations are in progress for S/S works.

RFQ for the P/S works package is likely to be floated in October 2022.

Get in touch with us for more on these projects