Rs 132 crore Construction of 132kV S/C on D/CTransmission Line : Conductor package in November 2022

The detailed survey and soil test have been completed for all the locations.

Additional compensation to the private land owners has been completed.

Forest clearance stage 1 has been granted and stage 2 is pending at the DFO

RFQ for the ACSR deer conductor package is likely to be floated in November 2022.

Rs 350 crore greenfield hydroelectric project : HM works package in Q4 2022

The forest clearance stage -1 and stage -2 have been granted by the DFO.

The owner has signed an agreement with ADB for funding the project.

EIA/EMP study was completed and it was approved by the MOEF

DPR has been completed and it was approved by CEA

The pre-bid meeting has been completed for the civil works package and major contractors have shown interest in meetings.

RFQ for the HM works package is likely to be floated in Q4 2022.

Rs 13000 crore greenfield pumped storage project: Drilling and drifting works in Q4 2022

TOR granted by the MoEF

Aravee Associates has prepared the PFR of the project.

The state cabinet committee has approved the project.

Construction of the approach road is in progress by the state PWD department.

RFQ for the drilling and drifting works is likely to be floated in Q4 2022.

Rs 16000 crore greenfield super thermal power project: Chlorine dosing system in October 2022

PG test yet to be conducted for BTG.

Erection of ESP has been completed for the first two units.

Sub-contractor has been selected for the absorber system.

RFQ for the Chlorine dosing system package is likely to be floated in October 2022.