Forest clearence stage-1 and stage-2 have been granted by DFO. – Software update: Power projects, 13 Sep 2022

Sep 13, 2022

Rs 850 crore greenfield combined cycle gas-based thermal power project: EPC package in Q4 2022

Geotechnical investigation and topographical survey have been completed.

EIA has been completed and it has not yet been accepted by the MoEF.

Development Consultants has prepared the DPR and it is yet to be approved by CEA.

The owner has signed an agreement with ADB for funding the project.

PPA was signed with the State Government.

RFQ for the EPC package for the main plant is likely to be floated in Q4 2022.

Rs 120 crore Construction of 220kV DC Transmission Line: P/S works in October 2022

Forest clearence stage-1 and stage-2 have been granted by DFO.

Techno Electric has been selected for sub-station works.

Approval from PTCC, Defence, and civil aviation is in progress.

RFQ for the P/S works is likely to be floated in October 2022.

Rs 4200 crore greenfield pumped storage project: Civil works package in November 2022

WAPCOS has prepared DPR and it is yet to be granted by the CEA.

FC stage-1 has been granted by DFO and FC stage-2 is pending at the regional office.

Drilling and drifting works at the site have been completed.

RFQ for the civil works package (Lot-1) is likely to be floated in November 2022.

Rs 10000 crore greenfield Off-stream pumped storage project: SIA consultant work in October 2022

The forest clearance stage -1 is pending at the nodal office.

The owner has selected Aravee Associates as a consultant for the preparation of DPR.

Geotechnical investigations and topographical surveys have been completed.

RFQ for the SIA consultant work is likely to be floated in October 2022.

Get in touch with us for more on these projects