Bulletin Updates

The Forest clearance 2 is pending at DFO. – Software update: Power projects, 8 Sep 2022

Sep 08, 2022

Rs 800 crore Construction of 400kV DC Transmission Line: S/S package in Q4 2022

The Forest clearance 2 is pending at DFO.

Soil test completed and pilling and foundation works are in progress for P/S.

Lattice tower works are in the initial phase of construction.

RFQ for the S/S works is likely to be floated in Q4 2022.

Rs 870 crore greenfield hydroelectric power project : Civil works package in November 2022

Forest clearance stage1 granted but stage 2 is pending at the nodal office.

DPR completed and report is under examination by CEA.

Hydrology report has been approved by CWC.

PMC selected for the project.

RFQ for the civil works package is likely to be floated in November 2022.

Rs 5180 crore brownfield super-critical thermal power project: Absorber system package in October 2022

PG test yet to be conducted for unit-2 BTG.

Mechanical completion for ESP is in progress and its PG test has been completed.

Erection and installation of the CW system are in progress and civil works for NDCT have been completed.

Civil and structural works for the installation of FGD are in progress

RFQ for the absorber system package is likely to be floated in October 2022.

Rs 1580 crore greenfield hydroelectric project: PMC works in Q4 2022

Three-season moon soon data collection has been completed and the hydrology report is pending at CWC.

Geotechnical investigation and topographical surveys have been completed and the report has been approved by GSI.

Drilling works at the project are in progress but drifting works are yet to be started.

RFQ for the PMC works is likely to be floated in Q4 2022.