RFQ for the SIA consultant works is expected by October 2022. – Software update: Power projects, 7 Sep 2022

Sep 07, 2022

Rs 1180 crore greenfield pump storage project: SIA consultant works in October 2022

Techno-commercial feasibility report has been approved.

Capital approval for the project has been granted by the state cabinet committee.

EIA/EMP consultant has been selected.

RFQ for the SIA consultant works is expected by October 2022.

Rs 650 crore greenfield hydroelectric project: PMC package in Q4 2022

The hydrological report has been approved by CWC.

WAPCOS has prepared the pre-feasibility report.

The geotechnical investigations and topographical survey at the site have been completed.

Drilling and drifting works at the site are in progress.

EQMS India Pvt. Ltd. has been selected as an EIA/EMP consultant.

RFQ for the PMC package is likely to be floated in Q4 2022.

Rs 450 crore greenfield hydroelectric power project: HM works package in November 2022

EC has been granted by the MoEF. Forest clearance stage -1 and stage - 2 has been granted by the DFO.

PMC was selected for the project.

The civil works contractor has been selected. Mobilization of equipment is in progress at the site.

RFQ for the HM works package is likely to be floated in November 2022.

Rs 320 crore construction of 132 kV D/C on S/C T/L: Conductor package in October 2022

Forest clearance 2 has been granted by the DFO.

Detailed survey and investigation have been completed for lattice tower erection

Private land acquisitions have been completed for the lattice tower.

Erection and installation works are in progress for the sub-station.

RFQ for the ACSR DEER conductor package is likely to be floated in October 2022.