Forest clearance stage 1 and 2 have been granted by the MoEF. – Software update: Power projects, 6 Sep 2022
Sep 06, 2022
Rs 531 crore Construction of 400kV QMDC Transmission Line: P/S package in October 2022
Forest clearance stage 1 and 2 have been granted by the MoEF.
Approvals fromr PTCC, civil aviation, and defense are in progress.
Soil test has been completed at the lattice tower location and fabrications are in progress.
ME Contractor selected for sub-station works.
RFQ for the 400 kV GiS S/S line is likely to be floated in October 2022.
Rs 11054 crore greenfield hydroelectric power project: PMC package in October 2022
DPR has been completed and it is under examination by CEA.
The forest clearance stage1 has been granted but stage 2 is under examination at the nodal office
GSI has approved the geotechnical investigation and the topographical survey reports for the project.
RFQ for the PMC package is likely to be floated in October 2022.
Rs 550 crore greenfield hydroelectric project: Civil works package (lot-1) in November 2022
The hydrological report has been approved by CWC.
The project faces some delays in the construction of approach land due to frequent landslides.
The forest clearance stage -1 and stage 2 have been accepted by the MoEF
RFQ for the civil works package (lot-1) is likely to be floated in November 2022.
Rs 1150 crore greenfield sub-critical thermal power project : DM plant package in Q4 2022
Coal import issue has been resolved by CIL.
Civil and structural works are in progress at the BTG site.
Sub-contractor selected for NDCT works.
Bidding is under progress for the CW system package.
Major sub-contractors are in the race for the CW system package.
RFQ for the DM plant package is likely to be floated in Q4 2022.