The RFQ for the SIA consultants is likely to be floated in October 2022. – Software update: Power projects, 1 Sep 2022
Sep 01, 2022
Rs 2020 crore greenfield hydroelectric project: SIA consultants in October 2022
The TOR for the same project was granted.
The owner has selected Mantect as an EIA consultant.
The application for forest clearance was pending at the nodal office.
The baseline report was accepted by the CWC and the hydrology report is in progress.
The RFQ for the SIA consultants is likely to be floated in October 2022.
Rs 1600 crore greenfield hydroelectric project: HM works package in Q4 2022
The DPR has been approved by the Godavari River Management Board.
The construction works are getting delayed due to harsh weather and inaccessible terrain.
Mobilization of construction equipment has been completed.
The pre-bid has been conducted for the civil works package(lot-2) and technical biddings are in progress.
The HM works are likely to be floated in Q4 2022.