Project Event: The company has applied for a loan, which is still under process, It is likely… – Software update: Fertilizer projects, 31 Aug 2022

Aug 31, 2022

Ammonia-Urea Energy Saving Project

Cost: Rs 250 Cr.

Project Event: The company has applied for a loan, which is still under process, It is likely to be elicited in Q3 FY 2022-2023, RFQ for the LSTK contractor is likely to be released in Q3 FY 2022-2023.

Single Super Phosphate Expansion Project

Cost: Rs 20 Cr.

Project Event: Detailed engineering work is still ongoing, The construction is likely to be started at the end of September 2022, They have their own engineering team, so they don't need a contractor. The commission is likely to be completed in December 2023