The RFQ for the Wagon Tripler package is likely to be floated in October 2022. – Software update: Power projects, 31 Aug 2022

Aug 31, 2022

Rs 5113 crore super-critical brownfield thermal power project: Wagon tripler package in October 2022

Decommissioning works at the site have been completed.

Pilling and foundation work at the BTG area have been completed.

Sub-contractor has been selected for the conveyor system

The RFQ for the Wagon Tripler package is likely to be floated in October 2022.

Rs125 crore construction of LILO 765kV Transmission line: P/S package in October 2022

The detailed survey and investigation were completed.

Approval from the civil and defense aviation department has been granted.

Contractor selected for S/S works. Civil works are in progress.

RFQ for the 765kV P/S works is likely to be floated in October 2022.

Rs 4400 crore greenfield hydroelectric project: PMC package in Q4 2022

The project got delayed due to the villager's protest and inaccessible terrain in the project area

The consultant has completed the detailed survey and investigation including a geotechnical investigation.

The hydrology report for the same has been completed and it was accorded by the CWC.

The RFQ for the PMC package is likely to be floated in Q4 2022.

Rs 4200 crore greenfield hydroelectric project: HM works package in Q4 2022

FC stage-2 has been granted by the DFO

Mobilization of equipment has been completed by the contractor.

Construction of the approach road has been completed.

The excavation works are in the active phase of construction.

The RFQ for the HM works package is likely to be floated in Q4 2022.

Get in touch with us for more on these projects