Bulletin Updates
RFQ for the 765 kV S/S works is likely to be floated in September 2022. – Software update: Power projects, 29 Aug 2022
Aug 29, 2022
Rs 820 crore construction of 765 kV D/c Transmission line: S/S works in September 2022
The forest clearance is pending at DFO.
Several meetings have been conducted with the landowner for transmission line works.
Detailed survey and investigation have been completed.
RFQ for the 765 kV S/S works is likely to be floated in September 2022.
Rs 8500 crore greenfield thermal project : Gypsum handling package in October 2022
PG tests have been completed for all units of BTG. Mechanical completion is underway.
The erection of all BOP works is in the advanced stage for completion.
The civil and architectural works were completed for the absorber system.
The RFQ for the limestone and gypsum handling system package is likely to be floated in October 2022.
Rs 4400 crore greenfield hydroelectric project : EPC package in Q4 2022
The E&M contractor has carried out the balanced design and engineering works of the E&M equipment.
Erection and installation of the Main Inlet Valve and Butterfly valve have been completed
Distilling chamber areas 1,2,3 is in progress slowly due to the Inadequate deployment of resources by the contractor.
The project is getting affected due to the slow progress of civil works and the cash flow crisis faced by the contractor.
Land acquisition works completed for power evacuation system.
The RFQ for the EPC package for the power evacuation system is likely to be floated in Q4 2022.
Rs 2880 crore greenfield hydroelectric project: Civil works package in Q4 2022
EIA and EMP studies have been completed.
Hydrology report is under examination by the CWC.
The pre-DPR chapter has been approved by the CEA.
The construction of the approach land to the dam site has been completed.
The RFQs for the civil works package are likely to be floated in Q4 2022.