Project Event: RFQ for Sindri HURL town ship has been out and bid due date is 7 September… – Software update: Fertilizer projects, 22 Aug 2022

Aug 22, 2022

Ammonia-Urea Brownfield Project

Cost: Rs. 6000 Cr.

Project Event: RFQ for Sindri HURL town ship has been out and bid due date is 7 September 2022. The project is likely to be commissioned in November 2022 in place of September 2022 due to the slow progress.98% of construction work has been completed. Pre- commissioning is ongoing.

Granular Single Super Phosphate Greenfield Project

Cost: Rs 148 Cr.

Project Event: The project has elicitedenvironmental clearance, and internal discussion is ongoing. RFQ for the LSTK contractor for SSP plant is likely to be released at the end of September in place of July 2022, due to delay in the discussion