FC stage -1 is pending at the nodal office. – Software update: Power projects, 22 Aug 2022

Aug 22, 2022

Rs 1800 crore greenfield hydroelectric project: 400 kV GIS S/S works in September 2022

The survey and investigation work for the T/L from the powerhouse to the common P/S has been completed

Mobilization has been completed. Excavation and boring works for HRT are in progress.

The techno-economic clearance and forest clearance (Stage-I&II) have been accorded.

The 400 kV GIS S/S works are likely to be floated in September 2022 instead of August 2022 due to delays in the P/S survey and investigation works.

Rs 5200 crore greenfield standalone pumped storage project: Civil works package(lot-1) in Q4 2022

The Water Resource Department and Energy Department have approved the project.

DPR is in the advanced stage for completion. Pre-DPR chapters have been approved by the CEA.

EIA/EMP and SIA studies are in progress and it is in the advanced stage of completion.

The Civil works package(lot-1) is likely to be floated in the second half of Q4 2022 instead of Q3 2022.

Rs 13000 crore greenfield standalone pumped storage project: SIA consultant in October 2022

Geotechnical investigation and topographical survey works were completed and the reports are under examination by GSI

FC stage -1 is pending at the nodal office.

Drilling and drifting works at the site are in progress.

RFQ for the SIA consultant is likely to be floated in October 2022.