The civil works package(lot-1) is likely to be floated in October 2022. – Software update: Power projects, 18 Aug 2022
Aug 18, 2022
Rs 1250 crore greenfield hydroelectric project: Civil works package (lot-1) in October 2022
The modification of DPR has been completed, after a glacier burst study was conducted as suggested by the CEA.
Modification in the hydrology report has been completed and it has been approved by CWC.
The PMC has been selected for the project.
Forest clearance stage 1 has been granted and stage 2 is in progress at the nodal office.
The civil works package(lot-1) is likely to be floated in October 2022.
Rs 1900 crore greenfield hydroelectric project: HM works in Q4 2022
The signing of the PPA was completed with the state government
Private land acquisitions were completed for transmission line works.
Forest clearance stage 2 is under process at the nodal office
Major civil works contractors showed interest in pre-bid meetings for civil works. (Get the list of all contractors)
The HM works package is likely to be floated in Q4 2022.
Rs 300 crore construction of 765 kV D/C Tower : P/S works in October 2022
Fabrication works are in progress for the lattice tower erection.
Land acquisition completed for S/S works.
Erection and installation of S/S are in progress.
P/S works package is likely to be floated in October 2022.
Rs 5200 crore greenfield hydroelectric project stage-II: EPC package in Q4 2022
The hydrology report has been approved by CWC.
DPR has been prepared by the M/S PDC Consultant and it has been approved by CEA
The project is getting delayed as the FC Stage 2 has been stuck at DFO.
The EPC package for civil and HM works is likely to be floated in Q4 2022.
Get in touch with us for more on these projects