Bulletin Updates

P/S works package is likely to be floated in September 2022. – Software update: Power projects, 17 Aug 2022

Aug 17, 2022

Rs 450 crore construction of 765 kV D/C tower: P/S works in September 2022

The pilling and foundation works were completed.

EPC selected for S/S works.

Private land acquisition was completed for S/S.

P/S works package is likely to be floated in September 2022.

Rs 4000 crore greenfield standalone pumped storage project : EM works in Q4 2022

The PPA was signed with the owner

Private land acquisitions and public hearings were completed.

Forest clearance stage 2 is under process at the regional office

The pre-bid meetings are about to conduct for the EPC package for civil and hydro-mechanical works.

The EM works package is likely to be floated in Q4 2022.

Rs 400 crore greenfield hydroelectric project: civil works package(lot-1) in Q4 2022.

The state PWD department has completed the approach road construction.

Drilling works at the site were completed and drifting works are in progress.

Hydrology report has been approved by CWC

Forest clearance stage 1 was granted by the DFO and stage 2 is in progress at the nodal office.

The civil works package(lot-1) is likely to be floated in Q4 2022.

Rs 4800 crore thermal power station replacement project: BOP works in October 2022

EPC has retained its terminated contracts as the verdict comes in favor of them.

Civil and structural works are in progress at the BTG site.

Civil and structural works for BOP are in progress

Sub-contractors selected for DM plant works.

PT plant package is likely to be floated in October 2022.

Get in touch with us for more on these projects

The full story is for subscribers. Log in to read it, or start a free trial.
Log in Start a free trial »