Ammonia-Urea Brownfield Project
Cost: 6500 Cr.
Project Event: RFQ for the additional Dryer unit has been out and bid due date is extended from 29 June to 25 August. Comt Construction Private Limited is the L1 bidder for the Sheeting Cladding in Wagon Loading Platform with a price bid INR 2,99,62, 250. Around 96 % of construction work has been completed, and the equipment installation is ongoing. Pre-commissioning is ongoing, Commercial production is likely to be started from September in place of June 2022, due to delay in the construction.
Ammonia-V Revamp Project
Cost: 102 Cr.
Project Event: RFQ for the Hot Water & Chilled water package has been out and due date is 23 August 2022. The project is likely to be commissioned in December 2022 in place of October 2022 due to the impact of Covid