Bulletin Updates
The 400 KV GIS S/S works package is likely to be floated in September 2022. – Software update: Power projects, 16 Aug 2022
Aug 16, 2022
Rs 290 crore construction 400 KV 2xD/C Transmission line: 400 kV GIS S/S works in September 2022
The approval from the PTCC, defense, and civil aviation departments has been granted.
Land acquisition has been completed for sub-station works.
The erection and fabrication of lattice tower works are in progress
The 400 KV GIS S/S works package is likely to be floated in September 2022.
Rs 653 crore greenfield hydroelectric project: EPC package in October 2022
The PPA was signed with State Government.
The FC stage-2 was pending at the nodal office for the diversion of forest land
The hydrology report has been approved by the CWC.
The EPC package for civil and HM works is likely to be floated in October 2022.
Rs 4508 crore greenfield hydroelectric project: civil works delayed
Constructed the approach road to the dam site has been completed.
The construction works getting delayed due to unexpected geological conditions at the site.
The expert geological team is likely to visit the site. Consultation is in progress
The HM works package is likely to be floated in Q4 2022.
Get in touch with us for more on these projects
Log in Start a free trial »

