The railway siding package-5 is likely to be floated in October 2022. – Software update: Power projects, 9 Aug 2022

Aug 09, 2022

Rs 10000 crore greenfield super-critical thermal power station project: Railway siding package-5 in October

Construction of railroads from coal mines to the project site is in progress.

Land demarcation and equipment mobilization works have been completed

Civil and structural, architectural, and excavation works for BOP are in progress

PT plant works and CW system works have just started

The railway siding package-5 is likely to be floated in October 2022.

Rs 5000 crore greenfield pumped storage project: Civil works package(lot-1) in Q4 2022.

The forest clearance Stage-1 was accepted and stage-2 is pending at DFO.

Drilling and drifting works for the same have been completed.

SIA report is not yet approved.

PMC selected for the project

The civil works package(lot-1) is likely to be floated in Q4 2022.

Rs 3000 crore greenfield hydroelectric power station : EM works in October 2022.

The revised CAT plan has been accepted by the State Government.

Forest clearance st-1 stage-2 has been granted DFO.

Private land acquisition and the public hearings have been completed.

The civil and HM works contractors have been selected.

The contractors have started the mobilization of equipment at the site.

The EM works package is likely to be floated in October 2022.

Rs 30 crore construction of 220 kV S/C on D/C Tower : EPC package in Q4 2022.

The forest clearance is pending at the nodal office for the diversion of 4.4476 Ha of forest land.

A detailed survey and investigation were completed and a soil test was completed for the tower side.

Private land acquisition was conducted for the transmission line

EPC package for the transmission line is likely to float in Q4 2022.

Get in touch with us if you want to know more about these projects