Bulletin Updates
FC stage -2 has been accorded by DFO – Software update: Power projects, 5 Aug 2022
Aug 05, 2022
Rs 450 crore 765KV D/C transmission line project :S/S package in September
FC stage -2 has been accorded by DFO
Erection of lattice tower is in progress.
Wildlife clearance has been granted.
8765 kV S/S works package is likely to be floated in September 2022.
Rs 800 crore greenfield pumped storage project : EPC package in Q4 2022.
EQMS India Pvt. Ltd. was selected as an EIA/EMP consultant.
Land acquisitions have been completed.
Aravee Associates selected as a DPR consultant
Drilling works at the site are in progress and drifting at the site is yet to be started
EPC package for the main plant works is likely to be floated in Q4 2022.
Rs 6000 crore greenfield pumped storage project: Drilling and drifting works in September.
MoEF&CC granted the TOR.
Geotechnical investigation report yet to be granted
Aravee Associates selected as a DPR consultant
Land acquisitions are in progress at the upper reservoir site.
The drilling and drifting works are likely to be floated in September 2022.
Rs 13000 crore greenfield super thermal power project: Absorber system in October.
High court has resolved the issue with the local fishermen.
The transportation of TG parts was completed at the site and fabrication works are in progress
The PMC was selected for the construction of unit-2 BTG
Sub-contractor was selected for railway siding works.
The absorber system package is likely to be floated in October 2022.
Get in touch with us if you want to know more about these projects
Log in Start a free trial »

